Day 42

Day 42 of FRC 2013 Build
Saturday
16 February 2013

The climbing system is almost complete. The electrical components for the climbing system has been installed. The only issue is that the team is missing a solenoid card for the CRio. We will receive a new solenoid card along with a new 4 slot cRio before the start of the Inland Empire Regional.



The climbing system itself was tested with the robot attached. The climbing system will propel the robot into level 1 of the pyramid.


Further troubleshooting of the robot continued today. We have resolved several issues with the program. We know for sure that the elevation system works. Further troubleshooting will continue through until the robot is bagged.